photo Reza Hapiz - Beritajakarta.id

Drilling for MRT Has Touched Senayan Station

The drilling for construction of Mass Rapid Transit (MRT) station has touched the Senayan Station.

The drilling machine has made a subway as long as 318 meters from Pemuda Senayan Statue until touching Senayan Station

PT MRT Jakarta Director, Dono Bustami said, until last December, the second Tunnel Boring Machine (TBM) or popularly known as "Antareja II" has touched Senayan Station. Antareja II was firstly operated in Pemuda Senayan Statue on November 11, 2015.

"The drilling machine has made a subway as long as 318 meters from Pemuda Senayan Statue until touching Senayan Station," he told, Tuesday (1/26).

MRT project Remains Priority

Antareja II has the same specification with Antareja I, which is having a diameter of ± 6.7 meters with total long ± 43 meters and its weight ± 323 tons, starting cutterhead until backup cars.

This coincided with tunnel installation, is in form of precast pieces with width 1.5 meters.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1221 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1056 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye911 personAldi Geri Lumban Tobing
  4. First Jakarta Update Talks Nataru up to Water Tariff Adjustment

    access_time24-12-2024 remove_red_eye825 personDessy Suciati
  5. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye737 personFolmer