Bor Antareja II Tembus Stasiun Senayan

Drilling for MRT Has Touched Senayan Station

The drilling for construction of Mass Rapid Transit (MRT) station has touched the Senayan Station.

The drilling machine has made a subway as long as 318 meters from Pemuda Senayan Statue until touching Senayan Station

PT MRT Jakarta Director, Dono Bustami said, until last December, the second Tunnel Boring Machine (TBM) or popularly known as "Antareja II" has touched Senayan Station. Antareja II was firstly operated in Pemuda Senayan Statue on November 11, 2015.

"The drilling machine has made a subway as long as 318 meters from Pemuda Senayan Statue until touching Senayan Station," he told, Tuesday (1/26).

MRT project Remains Priority

Antareja II has the same specification with Antareja I, which is having a diameter of ± 6.7 meters with total long ± 43 meters and its weight ± 323 tons, starting cutterhead until backup cars.

This coincided with tunnel installation, is in form of precast pieces with width 1.5 meters.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1086 personFakhrizal Fakhri
  2. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye992 personAldi Geri Lumban Tobing
  3. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye948 personAldi Geri Lumban Tobing
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye723 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye623 personAnita Karyati